Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 73982 REL 125: 1987-100-01 EXP UMATILLA ANADROMOUS FISH HABITAT - CTUIR
Project Number:
Title:
Umatilla Anadromous Fish Habitat-Umatilla Tribe
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Umatilla 100.00%
Contract Number:
73982 REL 125
Contract Title:
1987-100-01 EXP UMATILLA ANADROMOUS FISH HABITAT - CTUIR
Contract Continuation:
Previous: Next:
73982 REL 96: 1987-100-01 EXP UMATILLA ANADROMOUS FISH HABITAT - CTUIR
  • 73982 REL 150: 1987-100-01 EXP UMATILLA ANADROMOUS FISH HABITAT - CTUIR
Contract Status:
Closed
Contract Description:
During CY2021, the project will continue to work on coordination efforts, identification of new projects, planning and permitting, designs and construction. Permitting and designs will continue for the UmaBirch Floodplain Reconnection Project, located along the mainstem Umatilla River and Birch Creek. The CTUIR are also coordinating with the UBWC to complete designs on two fish passage projects on West Birch Creek. One of these is located on West Birch and the other site is located nearby on a major tributary (i.e. Stanley Creek). Designs will begin for the Meacham RM10-11 Floodplain Reconnection Project. Major construction projects will occur on the UmaBirch and Meacham Creek (Punchlist Project - Bonifer Reach).  Crews will also continue to maintain high priority project areas, treat weeds and complete all planting necessary within all project areas. Please refer to the respective Work Elements for a more detailed account of those specific projects.

Priorities:
  UmaBirch Project: this is a high priority project, based on the fact that it will impact all life history stages, for all aquatic organisms living
  within the Umatilla Basin. This project is addressing all of the high priority restoration actions within this high priority reach, as identified
  in the Birch Creek Assessment and Action Plan (CTUIR 2016).

  West Birch Fish Passage: these projects were identified as a high priority on the ODFW/ODOT list of priority fish passage projects. They  
  were also identified as a priority in the Birch Assessment (CTUIR 2016).

  Meacham Creek:
    RM 10-11: This is the next high priority area to complete a floodplain reconnection project following those projects already done, as
    identified in the previously completed watershed assessment (Andrus & Midell 2003).

    Meacham Punchlist: this was the previously identified priority restoration reach (Andrus & Midell 2003). This project has identified the
    addition of surface placed wood in strategic locations throughout the entire Bonifer Reach Project. This was deemed prudent before
    permits expired and following the two major flood events of this past spring (200+ year event, followed 3 months later by a 100-year
    event).

Account Type(s):
Expense
Contract Start Date:
02/01/2021
Contract End Date:
01/31/2022
Current Contract Value:
$1,768,284
Expenditures:
$1,768,284

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Effective implementation management and timely contract administration C: 119. Habitat Project Implementation Management and Contract Administration 01/31/2022 01/31/2022
Compliance documentation and assistance for environmental and cultural resource clearances D: 165. Environmental Compliance Clearance for ecological restoration and habitat enhancement projects 01/31/2022 01/31/2022
List of final projects E: 114. CTUIR Umatilla Subbasin Restoration Coordination 01/31/2022 01/31/2022
Coordinate watershed association activities F: 191. Umatilla River Watershed coordination duties 01/31/2022 01/31/2022
Complete outreach and education activities G: 99. Public Outreach and Education 01/31/2022 01/31/2022
Provide technical input and summaries to enhance or protect natural resources in the subbasin. H: 122. Review and provide technical input on issues and topics that affect the area's natural resources 01/31/2022 01/31/2022
Maintain proper operation of instream habitat structures I: 186. Inspect and maintain function of instream improvement structures 01/31/2022 01/31/2022
Maintenance of habitat features associated with project conservation agreements J: 186. Maintenance of habitat features associated with project conservation agreements 01/31/2022 01/31/2022
Maximize survival of native vegetation in enhancement project areas. K: 198. Enhance native vegetation by noxious weed control within Umatilla River Subbasin project areas 01/31/2022 11/30/2021
Produce documents and surveys necessary for the conservation easement L: 172. Conduct pre-aquisition activities for Birch Creek-Umatilla River confluence and East Birch Properties 01/31/2022 01/31/2022
Draft Umatilla River Subbasin Assessment and Action Plan M: 115. Produce Umatilla River Subbasin Assessment 01/31/2022 12/31/2021
Meacham Creek RM 10 Habitat Enhancement Design N: 175. Meacham RM 10 Habitat Enhancement Project Design 01/31/2022
100% UmaBirch Floodplain Restoration and Habitat Enhancement Design O: 175. UmaBirch Properties - Floodplain Restoration and Habitat Enhancement Draft Designs 01/31/2022 01/31/2022
Create Floodplain Complexity P: 29. Construction - Meacham Creek Punchlist 01/31/2022 08/13/2021
Complete scheduled tree and shrub plantings in project areas Q: 47. Planting within Umatilla River Subbasin project areas 01/31/2022 12/31/2021
Remove Levees and Spur Dikes R: 180. Construction - Meacham Creek Punchlist 12/31/2021 08/13/2021
Imeques Reach Habitat Enhancement Final Design T: 175. Imeques Reach Project Design 01/31/2022
Final Design U: 175. West Birch Creek Fish Passage Project Design 01/31/2022

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 1 instance of WE 198 Maintain Vegetation
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 2 instances of WE 175 Produce Design
Coho (O. kisutch) - Unspecified Population
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 2 instances of WE 175 Produce Design
Steelhead (Oncorhynchus mykiss) - All Populations
  • 1 instance of WE 175 Produce Design
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 198 Maintain Vegetation
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 184 Install Fish Passage Structure
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 3 instances of WE 175 Produce Design
Lamprey, Pacific (Entosphenus tridentata)
  • 1 instance of WE 175 Produce Design
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 198 Maintain Vegetation
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 1 instance of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA
B 132 Progress Report: Calendar- Year 2021 (01/01/2021 - 12/31/2021)
C 119 Habitat Project Implementation Management and Contract Administration
D 165 Environmental Compliance Clearance for ecological restoration and habitat enhancement projects
E 114 CTUIR Umatilla Subbasin Restoration Coordination
F 191 Umatilla River Watershed coordination duties
G 99 Public Outreach and Education
H 122 Review and provide technical input on issues and topics that affect the area's natural resources
I 186 Inspect and maintain function of instream improvement structures 02/01/2021
J 186 Maintenance of habitat features associated with project conservation agreements 05/01/2021
K 198 Enhance native vegetation by noxious weed control within Umatilla River Subbasin project areas 05/01/2021
L 172 Conduct pre-aquisition activities for Birch Creek-Umatilla River confluence and East Birch Properties
M 115 Produce Umatilla River Subbasin Assessment 02/01/2021
N 175 Meacham RM 10 Habitat Enhancement Project Design 02/01/2021
O 175 UmaBirch Properties - Floodplain Restoration and Habitat Enhancement Draft Designs 02/01/2021
P 29 Construction - Meacham Creek Punchlist 06/01/2021
Q 47 Planting within Umatilla River Subbasin project areas 03/31/2021
R 180 Construction - Meacham Creek Punchlist 07/01/2021
S 184 West Birch Creek Fish Passage Project Implementation
T 175 Imeques Reach Project Design 09/20/2021
U 175 West Birch Creek Fish Passage Project Design